1 | Approval of electrical layout and single line diagram from ABCI/DES | 2 | 5 | 76 | 88 |
2 | Payment of connection charges | 1 | 2 | 83 | 89 |
3 | Approval for permit to dig | 11 | NA *No application requires permit to dig to date
| NA *No application requires permit to dig to date
| |
4 | Approval for permanent connection | 3 | 4 | 58 | 93 |